Current Localflex Competitions
Browse the current flexibility competitions…
Competition Window
19 August - 2 September
Location
Torbay & Waiake feeders
Capacity
2–3 MW required
Service
Demand turn-down / generation turn-up
Products
Long-Term Scheduled Utilisation
Scheduled Availability
Operational Utilisationer
Delivery
Winter 2027 & 2028
Winter 2029 & 2030
Pricing
$151–360/MWh utilisation
$80/MW/hr availability
Competition Window
19 August - 2 September
Location
Castlecliff and Tower Rd substations, Bethlehem feeder
Capacity
0.18–1.7 MW required
Service
Demand turn-down / generation turn-up
Products
Long-Term Scheduled Utilisation
Delivery
Winter 2028 (April/May–August)
Pricing
$120–415/MWh utilisation
Competition Window
19 August - 2 September
Location
Kope substation
Capacity
Up to 1.6 MW required
Service
Demand turn-down / generation turn-up
Products
Long-Term Scheduled Utilisation
Delivery
Winter 2027, 2028 & 2029 (June–July)
Pricing
$390–440/MWh utilisation
Competition Window
19 August - 2 September
Location
Church Rd substation
Capacity
Up to 0.5 MW required
Service
Demand turn-down / generation turn-up
Products
Long-Term Scheduled Utilisation