Localflex competitions

Browse flexibility competitions offered by participating electricity networks across New Zealand.

Competition Window
19 August - 16 September 2026

Location
Torbay & Waiake feeders

Capacity
2–3 MW required

Service
Demand turn-down / generation turn-up

Products

  • Long-Term Scheduled Utilisation

  • Scheduled Availability, Operational Utilisation

Delivery
Winter 2027, Winter 2028, Winter 2029, Winter 2030

Pricing
$151–360/MWh utilisation
$80/MW/hr availability

Competition Window
19 August - 16 September 2026

Location
Castlecliff and Tower Rd substations, Bethlehem feeder

Capacity
0.18–1.7 MW required

Service
Demand turn-down / generation turn-up

Products

  • Long-Term Scheduled Utilisation

Delivery
Winter 2028 (April/May–August)

Pricing
$120–415/MWh utilisation

Competition Window
19 August - 16 September 2026

Location
Kope substation

Capacity
Up to 1.6 MW required

Service
Demand turn-down / generation turn-up

Products

  • Long-Term Scheduled Utilisation

Delivery
Winter 2027, 2028 & 2029 (June–July)

Pricing
$390–440/MWh utilisation

Competition Window
19 August - 16 September 2026

Location
Church Rd substation

Capacity
Up to 0.5 MW required

Service
Demand turn-down / generation turn-up

Products

  • Long-Term Scheduled Utilisation

Delivery
Winter 2028 (June–August)

Pricing
$406/MWh utilisation

Participating networks

Participating flexiblity service providers

“We know that smart, local energy systems can and will be an integral part of our decarbonisation journey - many local producers are doing it now, with our help.”

John Campbell, CEO & Founder, Our Energy

Our Energy is the exclusive distribution partner of Localflex in New Zealand & Australia